top of page

Project Item Details

We kindly ask you to complete the form provided below. This form is an important step in confirming your project items we need for planning on for our end.

Hi Erin!


Please see below for your project item details that:

  • are needed

  • need review or approval

  • need to be confirm

  • need timeline - order date and on-site date

______________________________________

INTERIOR FINISH MATERIALS

Crown | Please Confirm: NONE
Confirming, NONE
Dependent/Other, To Discuss
Recessed Outlet Box for TV | Would you like to replace the standard with this (we recommend for mounting tv) no cost to change
Yes
No
Garage Interior Hardware (No Lock Set) Links Below for Review and Approval
Option 1
Option 2
None of these
Shoe Molding | Please Confirm: NONE
Confirming, NONE
Dependent/Other, To Discuss
Grout | Please Confirm: DESIGNER SUPPLYING
Confirming, DESIGNER SUPPLYING
NO, would like CONTRACTOR to supply

______________________________________

EXTERIOR FINISH MATERIALS

Siding White Vinyl and Azek Trim | Please Confirm: To Match Exisiting
Confirming, MATCH EXISITING
NO, other to discuss
Entry and Kitchen Exterior Door Hardware Options (Lock Set) | Please review these for approval
Option 1
Option 2
None of these

______________________________________

OUTSTANDING ITEMS UNTIL ACTIVE CONSTRUCTION | NO ACTION AT THIS TIME

______________________________________

DUE AT START OF CONSTRUCTION TENTATIVE WEEK OF 12/16